Environment Minister George Heyman, Premier John Horgan and Energy Minister Michelle Mungall announce that B.C. Hydro is proceeding with construction of the Site C dam, Dec. 11, 2017. (Tom Fletcher/Black Press)

Environment Minister George Heyman, Premier John Horgan and Energy Minister Michelle Mungall announce that B.C. Hydro is proceeding with construction of the Site C dam, Dec. 11, 2017. (Tom Fletcher/Black Press)

B.C. VOTES 2020

Site C actions, costs won’t be known until after B.C. election, Horgan says

Peace River diverted for construction of reinforced dam base

The Peace River’s flow is now diverted through twin tunnels for the main riverbed works of B.C. Hydro’s Site C dam, opening a dry area of the riverbed for construction of “foundation enhancements” that were identified by geological mapping as a change to the project in late 2019.

The river diversion proceeded on schedule starting Oct. 2, but the additional work and COVID-19 delays mean the completion date and additional costs remain uncertain, NDP leader John Horgan acknowledged in his final campaign event in Vancouver Thursday.

This week B.C. Hydro announced three positive tests for COVID-19 on the site near Fort St. John, and the start of burning wood debris captured from the river to keep diversion tunnels clear.

Newly sworn in as premier in 2017, Horgan called for the B.C. Utilities Commission to make a rapid review of the project, which by then had $4 billion invested in the long-considered third dam on the Peace River. That review was “inconclusive,” Horgan said, and the NDP government decided to proceed at a projected cost increased by $1 billion to $10.7 billion.

RELATED: Site C dam set back by COVID-19, foundation changes

RELATED: NDP government bails out B.C. Hydro for $1.1B debt

RELATED: After losing at every level, West Moberly sues again

B.C. Hydro’s annual report in July 2020 notified the government and public of the latest problems, including delays due to COVID-19 restrictions on the huge job site as well as the new geological issues. Before calling the election, then-energy minister Bruce Ralston appointed former deputy finance and transportation minister Peter Milburn to assess the project again.

“But now we are three and a half years later, and new evidence that was not presented at that time is being examined by Mr. Milburn,” Horgan said Oct. 22. “This is absolutely serious for Hydro ratepayers and for the project. I don’t want to diminish it in any way. But I don’t know until I hear from the experts what’s the magnitude of the problem, and what steps we need to take to protect British Columbians.”

In a July progress report to the B.C. Utilities Commission, B.C. Hydro CEO Chris O’Riley said the combined effects of COVID-19 and a series of construction issues have pushed the cost up by an amount not yet known. Those included changes to the main civil works contract, increased costs of reservoir clearing, power line construction and highway realignment, as well as the latest of a series of legal challenges from the West Moberly First Nations.

“Towards the end of December 2019, investigations and analysis of geological mapping and monitoring activities completed during construction identified that some foundation enhancements would be required to increase the stability below the powerhouse, spillway and future dam core areas,” O’Riley wrote in a letter to BCUC chair David Morton.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC politicsBC Votes 2020Site C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Chris Veale, seen here at Brookswood Secondary School on Sunday, Nov. 29, 2020, has been coaching girls basketball for more than 20 years (Dan Ferguson/Langley Advance Times)
Coach Chris Veale backs his players

When the gym closed, this dedicated basketball coach found another way

Submit letters to the editor through our website, via email or in writing.
LETTER: Government drives up cost of affordable housing

An Ottawa developer digs into building costs after reading about Langley’s new affordable housing

Tabor Village took to social media on Wednesday, Dec. 2, 2020 to share what it meant to them to have Langley Lodge staff visit and provide support. As of Tuesday (Dec. 1), the outbreak at Tabor had resulted in a total of 147 cases and 19 deaths since Nov. 4. (Tabor Village/Facebook)
Langley Lodge shows ‘solidarity’ by visiting staff of B.C.’s largest COVID-19 care-home outbreak

As of Tuesday, Abbotsford facility recorded 147 cases and 19 deaths since Nov. 4

Brian Lott, of the Rotary Club of Langley Central, emceed the prize draw on Thursday, Dec. 3, 2020. (Heather Colpitts/Langley Advance Times)
Langley woman wins $73,615 in first ever Langley Rotary Mega Draw

After months of ticket sales, the draw was livestreamed from the Rotary Interpretive Centre Thursday

B.C. Supreme Court in Vancouver. (Black Press Media files)
‘No smoke, no fire’ defense says in conflict case that could kick three off Langley Township council

Lawyers argued there’s no evidence of any conflict or vote-for-money deal

Motorists wait to enter a Fraser Health COVID-19 testing facility, in Surrey, B.C., on Monday, Nov. 9, 2020. THE CANADIAN PRESS/Darryl Dyck
Another 694 diagnosed with COVID-19 in B.C. Thursday

Three more health care outbreaks, 12 deaths

Cops converge in a Marshall Road parking lot on Thursday afternoon following a reported police incident. (Ben Lypka/Abbotsford News)
Federal offender escapes, gets shot at and is taken back into custody in Abbotsford

Several branches of law enforcement find escapee a short distance from where he fled

A demonstrator wears representations of sea lice outside the Fisheries and Oceans Canada offices in downtown Vancouver Sept. 24, demanding more action on the Cohen Commission recommendations to protect wild Fraser River sockeye. (Quinn Bender photo)
First Nations renew call to revoke salmon farm licences

Leadership council implores use of precautionary principle in Discovery Islands

Ten-month-old Aidan Deschamps poses for a photo with his parents Amanda Sully and Adam Deschamps in this undated handout photo. Ten-month-old Aidan Deschamps was the first baby in Canada to be diagnosed with spinal muscular atrophy through Ontario’s newborn screening program. The test was added to the program six days before he was born. THE CANADIAN PRESS/HO, Children’s Hospital Eastern Ontario *MANDATORY CREDIT*
First newborn tested for spinal muscular atrophy in Canada hits new milestones

‘If Aidan had been born any earlier or anywhere else our story would be quite different’

Cannabis bought in British Columbia (Ashley Wadhwani/Black Press Media)
Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

(Pixabay)
Canadians’ mental health has deteriorated with the second wave, study finds

Increased substance use one of the ways people are coping

Surrey Pretrial centre in Newton. (Photo: Tom Zytaruk)
Surrey Pretrial hit with human rights complaint over mattress

The inmate who lodged the complaint said he needed a second mattress to help him manage his arthritis

A coal-fired power plant seen through dense smog from the window of an electric bullet train south of Beijing, December 2016. China has continued to increase thermal coal production and power generation, adding to greenhouse gas emissions that are already the world’s largest. (Tom Fletcher/Black Press)
LNG featured at B.C. energy industry, climate change conference

Hydrogen, nuclear, carbon capture needed for Canada’s net-zero goal

Most Read