Environment Minister George Heyman, Premier John Horgan and Energy Minister Michelle Mungall announce decision to proceed with construction of the Site C dam, B.C. legislature library, Dec. 11, 2017. (Ragnar Haagen/Black Press)

Site C dam goes ahead, cost estimate now up to $10.7 billion

Premier John Horgan says Christy Clark left him no other choice

B.C. Premier John Horgan has given the green light to completion of the Site C hydroelectric dam, after B.C. Hydro revised its cost estimate upward by more than $1 billion.

The B.C. NDP cabinet has struggled with the decision, with the project two years in and facing a cost of $4 billion to shut down construction of the third dam on the Peace River and put the site back the way it was.

After hearing from experts for weeks, the government faced an estimate that B.C. Hydro rates are already expected to rise 30 per cent over the next 10 years without the costs of Site C.

If the dam is halted, rates would go up another 12 per cent by 2020 to pay the cost. That translates to an extra $198 per year for an average single-family house.

RELATED: How Christy Clark made Site C unstoppable

When it proceeds, government officials expect the additional rate increase would be 6.5 per cent when the dam goes into service in 2024. B.C. Hydro would likely apply to the B.C. Utilities Commission to “smooth” that rate increase, raising it in smaller steps to pay for the dam.

Horgan blasted the previous B.C. Liberal government for “megaproject mismanagement” that left the NDP government with little choice.

“It’s clear that Site C should never have been started,” Horgan said. “But to cancel it now would add billions to the province’s debt – putting at risk our ability to deliver housing, child care, schools and hospitals across B.C. And that’s a price we’re not willing to pay.”

The risk reserve for Site C has been increased by $700 million to prepare for further costs increases.

B.C. Liberal critic Mike Bernier, MLA for Peace River South, said the project had been studied for a decade and 2,000 families and Peace region businesses have been left with uncertainty while the new government’s review carried on.

B.C. Liberal finance critic Tracy Redies, a former B.C. Hydro board member, said the NDP’s review confirmed that with projected growth in electricity demand, B.C. will need the equivalent of nine Site C dams by 2050.

B.C. Green Party leader Andrew Weaver said proceeding with Site C was a result of the NDP “pandering for votes” by taking $4.7 billion of Port Mann bridge debt onto the government books to cancel bridge tolls.

Now the province can’t afford the $4 billion cost of stopping the dam, and it has two bad policies based on political expediency, Weaver said.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Just Posted

Mounties need help finding Langley woman

Familiy haven’t spoken to Megan Terpsma much since June 2017, and concerned for her well-being.

VIDEO: ERT descends on Langley property Wednesday

Several law enforcement agencies were seen at a Willoughby home.

Not too bad for a Langley boy who didn’t really like volleyball

Daniel Jansen VanDoorn is playing with the Canada Team in men’s volleyball world championships.

VIDEO: Gateway to Aldergrove mural celebrated

Artists and sponsors join Kitchen Korner in marking downtown arts achievement

A call for a limit on how long Langley councillors can serve

Veteran council member says four terms should be the maximum

VIDEO: Messages of hope, encouragement line bars of B.C. bridge

WARNING: This story contains references to suicide and may not be appropriate for all audiences.

Fresh-faced Flames fend off Canucks 4-1

Vancouver drops second straight NHL exhibition contest

VIDEO: B.C. deer struggles with life-preserver caught in antlers

Campbell River resident captures entangled deer on camera

Scheer pushes Trudeau to re-start Energy East pipeline talks

Conservative Leader Andrew Scheer questioned the Prime Minister over Trans Mountain project

Mistaken identity: Missing dog claimed in Moose Jaw belongs to another family

Brennen Duncan was reunited with a white Kuvasz that was found in Saskatchewan

Abandoned kitten safe and sound thanks to B.C. homeless man

‘Jay’ found little black-and-white kitten in a carrier next to a dumpster by a Chilliwack pet store

Police chief defends controversial marijuana seizure

Advocates said cannabis was part of an opioid-substitution program in Vancouver’s Downtown Eastside

Trans Mountain completes Burrard Inlet spill exercise

Training required, some work continues on pipeline expansion

Supporters of B.C. man accused of murdering Belgian tourist pack courtoom

Family and friends of Sean McKenzie, 27, filled the gallery for brief court appearance in Chilliwack

Most Read