Langley’s Tybo Contracting undertook the $25.5-million highway widening project in July 2018, it was largely completed by December 2019. (Tybo photo)

Aldergrove reportedly less crowded at the U.S. border

Going from two to five lanes on Hwy. 13 will ‘ease local traffic’, says BC Ministry of Infrastructure

The south section of Highway 13 is nearly complete, as all five lanes at Aldergrove-Lynden border crossing are now open to traffic. But there’s still work to be done.

It was in July 2018 that shovels first hit the ground for the $25.5-million widening project that saw Highway 13, from Zero Avenue to 8th Avenue, widened by Langley’s Tybo Contracting.

Since then, with the exception of winter, construction workers have crowded areas from Aldergrove leading up to the U.S. border.

Formerly, the Aldergrove-Lynden border crossing had only two lanes for through traffic.

Now, two lanes take motorists north and three south – including a commercial vehicle lane, one passenger vehicle lane and a lane for general traffic which will become a Nexus lane.

The BC Ministry of Infrastructure is in the process of collecting data on reduced congestion as a result of the five-lane completion in Dec. but “these are the early days,” it said, and additional lanes have only been in operation for over a month.

The upgrades are expected to provide safety and efficiency benefits to local traffic, international travellers, and commercial vehicles through easing traffic queues by providing more capacity at this busy border crossing, the ministry told the Aldergrove Star in a statement.

The Nexus and truck lanes alone are expected to absorb about 30 per cent of the total traffic at the crossing, the ministry said previously.

It added that the improvements will, in turn “help tourism and trade,” as well as save time for people who live and work in the region.

READ MORE: Border expansion underway in Aldergrove

As of Friday at 1 p.m. there was no delay on wait times for everyday passengers at the crossing, according to the ministry’s online website.

What is still left to be done by the contractors, who are currently on a “temporary winter shutdown,” according to the ministry, includes 500 metres of the paving to 8th Avenue.

This includes the Highway 13 and 8th Avenue intersection and slope stabilization for the route.

Tybo Contracting is expected to start up work again sometime in March or April, depending on the weather.

The ministry anticipates final paving to occur by early spring 2020, at which time the section of road will open to four lanes.

Other newly completed parts of the project include a 3B Avenue east-west connection between Highway 13 and 264th Street, with a traffic signal at Highway 13.

There are also now wider paved shoulders for pedestrians and cyclists.

Less than half of the contract, $10 million, was paid for by the federal government.

The rest has been picked up by the province.

Get local stories you won't find anywhere else right to your inbox.
Sign up here

 

The completion of the Aldergrove-Lynden border crossing’s five-lane expansion will mean increased safety and decreased traffic jams along the south end of Highway 13, says the BC Ministry of Infrastructure. (Ministry of Transportation)

Just Posted

Vandals deface Aldergrove elementary school with racist slur, male genitalia

Langley School District confirms it has filed a report with the Langley RCMP

‘Our hands are tied’: Langley Good Times Cruise-In announces cancellation due to COVID-19

People are encouraged to donate to the chosen Langley charities online, said Cruise-In director

Rideshare expands into Aldergrove

As of Thursday, Lyft is now offering service throughout Metro Vancouver

Conservationists in race against time to rehabilitate grizzly cubs transferred to Aldergrove zoo

‘Let them be assessed now before their fate is sealed,’ urges B.C. conservationist Barb Murray

Pink flags on Langley church grounds raise awareness about sex-selective abortion

On Saturday, 1,000 pink flags will be placed on the lawn of Christ Covenant Church

B.C. sees 25 new COVID-19 cases, community exposure tracked

One death, outbreaks remain in two long-term care facilities

VIDEO: Vancouver Island cat missing 18 months reunited with family

Blue the cat found at Victoria museum 17 kilometres from home

VIDEO: Alberta man rescues baby eagle believed to be drowning in East Kootenay lake

Brett Bacon was boating on a lake in Windermere when he spotted the baby eagle struggling in the water

Police nab three impaired drivers in one night in Maple Ridge

Ridge Meadows RCMP served 80 impaired driving infractions in June

B.C.’s COVID-19 job recovery led by tourism, finance minister says

Okanagan a bright spot for in-province visitor economy

National Kitten Day aka the ‘purrfect’ day to foster a new friend

July 10 marks National Kitten Day, a special day to celebrate all things kittens

Lower Mainland YouTubers claim to be Kelowna display toilet ‘poopers’

RCMP can not speak to legitimacy of video, will be investigating

Haida matriarchs occupy ancient villages as fishing lodges reopen to visitors

‘Daughters of the rivers’ say occupation follows two fishing lodges reopening without Haida consent

Conservatives say police should be called into investigate WE charity scandal

Trudeau is already under investigation by the ethics commissioner for potential conflict of interest

Most Read