Site C work camp construction nears completion in April 2016. Called Two Rivers Lodge, the camp cost $470 million to build and operate and is a self-contained community with an 800-seat dining room, hair salon, gym, movie theatre and private room accommodations. (B.C. Hydro)

Environmental groups slam NDP decision to continue with Site C

Construction industry, meanwhile, is cautiously optimistic about how the project will look

Environmental groups denounced Premier John Horgan as he announced Monday the province would continue to build the Site C dam.

The Wilderness Committee told Black Press they were “massively disappointed” with what they called the NDP’s “flip-flopping” on the now-$10.7-billion northern B.C. megaproject.

“We can only come to the conclusion that Horgan was lobbied extensively by some of the construction unions,” said national campaign director Joe Foy.

READ: Site C dam goes ahead, cost estimate now up to $10.7 billion

According to the organization, the Site C dam could flood 83 kilometres of the Peace River from near Fort St. John upstream to Hudson’s Hope, contaminating fish stocks, and remove farmland from the Agricultural Land Reserve.

Foy took issue with the province’s claim that it would have cost $4 billion to halt the project, as well as Horgan’s stance that that money could not be paid back over time.

“We believe that is grossly overestimated,” he said. “All that dam can do, unlike the hole in the ground which just sits there, is lose us hundreds of millions of dollars every year it operates.”

He said the NDP’s decision could change B.C.’s political landscape as NDP voters who may feel betrayed move away from the party. Horgan had campaigned earlier this year on a promise to review, not kill, the dam, but he had criticized the BC Liberals’ approach to the project in the past.

More lawsuits expected

Court challenges, Foy said, are likely coming both from environmental and First Nations groups.

“I think rolling over First Nations in this way is unacceptable,” he said. “I think we will begin to see the effects of protests.”

Amnesty International called Horgan’s decision “a blatant betrayal of his government’s commitments to uphold the rights of Indigenous peoples.”

The group called foul on the province’s claim that it was too late to stop the project and said the West Moberly and Prophet River First Nations will continue their legal efforts.

‘We are relieved’

Meanwhile, the Independent Contractors and Businesses Association celebrated the thousands of jobs they believe will be kept and created by continuing work on Site C.

Spokesperson Jordan Bateman said all the extra time the NDP government took to have the dam reviewed was unnecessary, only to have Horgan ultimately go forward.

READ: BC Utilities Commission completes Site C report

Bateman said he also doesn’t buy the province’s new $10.7-billion estimated price tag. When it was approved by the then-Liberal government in 2014, the project was estimated at $8.8 billion.

“You have one analysis done in six weeks that says it could run over budget,” he said. “Frankly, the overruns that the NDP are planning for here are going to be caused by the NDP.”


@katslepian

katya.slepian@bpdigital.ca

Like us on Facebook and follow us on Twitter.

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

VIDEO: Record turnout for third annual Langley car show against cancer

Brogan’s Diner Fight Against Cancer Car Show was turned into a road trip because of COVID-19

Langley artist Lalita Hamill launches new website to showcase art and share instructional videos

A Zoom session on Saturday, July 18, will serve as a free art assessment and critique at 10 a.m.

Provincial COVID-19 data can now be used for B.C. to prepare for a second wave

In the past week, B.C. has seen a slight spike in daily test-positive case counts

Ryan’s Regards: Will the air travel industry once again take flight?

With airlines grounded and staff laid off, going abroad could be more difficult beyond COVID-19

‘It’s really frustrating’: B.C. Indigenous groups share impact of border closures

The closures have resulted in disputes between Indigenous groups and local businesses

Trudeau apologizes for not recusing himself from WE decision

He says his and his family’s longtime involvement with the WE organization should have kept him out of the discussions

Wage subsidy will be extended until December amid post-COVID reopening: Trudeau

Trudeau said the extension will ‘give greater certainty and support to businesses’

Beverly Hills 90210 star’s family selling Vancouver Island Beach Resort

You can own Jason Priestley’s Terrace Beach Resort in Ucluelet for less than $5 million

Islanders want BC Ferries to follow order that lets residents board before tourists

For ferry-dependent communities, ferries are often the sole practical lifeline to work, school or medical appointments.

Washington’s NFL team drops ‘Redskins’ name after 87 years

The franchise was given the name back in 1933, when it was still in Boston

Fraser Valley loses the Keith Wilson Waver as Ron Hupper passes away

Hupper brought smiles to the faces of hundreds of people traveling Chilliwack’s Keith Wilson Road

Genetic detectives begin work to trace spread of COVID-19 in Canada

The kinds of genetic technology being used for this project did not exist when SARS hit Canada in 2003

Most Read