Diversion tunnels have been completed to redirect the Peace River during low water this summer and fall, in one of the most critical steps to completing the Site C dam, March 2020. (BC Hydro)

B.C. Hydro’s Site C set back by COVID-19, foundation changes

Peace River diversion still on track for this fall

B.C. Hydro’s plan to have the third dam on the Peace River complete and in service by 2024 has been set back by work scaling down due to COVID-19 restrictions on construction projects, and additional foundation strengthening for the powerhouse and spillway.

In a progress report filed with the B.C. Utilities Commission July 31, B.C. Hydro CEO Chris O’Riley says the Site C project is still on track to divert the Peace River through a pair of tunnels and begin in-river work. But that too has been complicated by geological conditions. The financial impact of the coronavirus delays and additional work will be better known in the fall, O’Riley said.

“Pandemic-related delays will present further cost pressure on the budget,” O’Riley wrote in a letter to BCUC chair David Morton. “As the evolution of the pandemic is uncertain and the date of resolution is unknown, various cost and scheduled impact scenarios continue to be assessed and refined as part of the re-baselining process.”

The incoming NDP government reluctantly decided to carry on with Site C, after former premier Christy Clark vowed to push the project “past the point of no return” before the 2017 B.C. election. In doing so, Premier John Horgan approved an updated cost estimate of $10.7 billion to complete it, an increase of about $1 billion from the initial estimate.

RELATED: Site C dam project carries on under NDP government

RELATED: NDP pays off $1.1B in B.C. Hydro debt, seeks rate cut

RELATED: After losing at every level, West Moberly sues again

Now the combined effects of COVID-19 and a series of problems have pushed the cost up by an amount not yet known. Those issues included changes to the main civil works contract, increased costs of reservoir clearing, power line construction and highway realignment, and first nations treaty infringement claims and an injunction application.

“Towards the end of December 2019, investigations and analysis of geological mapping and monitoring activities completed during construction identified that some foundation enhancements would be required to increase the stability below the powerhouse, spillway and future dam core areas,” O’Riley wrote.

Before the COVID-19 pandemic, Site C was on track for completion by fall 2023 and full service to the B.C. Hydro grid by 2024.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislatureCoronavirusSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

LETTER: Pitt Meadows man calls on B.C. government to better fund parks

Investment in parks will pay off for the future, letter writer says

VIDEO: Rolled over truck at Langley roundabout knocks out streetlight

Driver treated from minor injuries, witness reports

Man, 31, in critical condition after altercation at Langley Trinity Western University

RCMP received a report of an ‘agitated man’ on campus

Westbound Highway 1 stall in Langley blocking left lane

Congestion starting at 264th Street, crews on scene

B.C. counts 125 new COVID-19 cases, up to 1,284 active

No new deaths or health care facility outbreaks

Man pleads guilty to violent assault of elderly man in Abbotsford

Victim, 85, attacked while waiting at bus stop in November 2019

Lessons from a pandemic: How to design a nursing home that’s safe and love-filled

A look at how one care home is battling the pandemic with the social needs of the elderly in their care

Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

Join Black Press Media and Do Some Good

Pay it Forward program supports local businesses in their community giving

Winter tires, chains now mandatory along most B.C. highways

Drivers without the proper winter tires – which must also be in good condition – can be fined $109

Staff shortages plague Mission Institution following recovery from COVID-19 outbreak

Guards at 60% of workforce; inmates suffer daily with lockdown, mental health issues

Health Canada green-lights rapid COVID-19 test

Health Canada approved the BCube test from Hyris Ltd. in the United Kingdom Sept. 23

First Nations Health Authority chief medical officer concerned with rising COVID-19 cases

“There’s still so much we don’t know and we’re learning everyday about this particular virus.”

Most Read