Slope stabilization work continues on the north bank of the Peace River for the Site C dam, September 2017. (B.C. Hydro)

UPDATE: Decision time for John Horgan on Site C dam

Energy Minister Michelle Mungall says delaying it is off the table

Premier John Horgan’s cabinet intends to make a decision on whether to continue building the most expensive construction project in B.C. history by the end of 2017.

The B.C. Utilities Commission released its independent report on the project Wednesday, ordered by Horgan to fulfil a promise he has repeated many times since becoming NDP leader.

The BCUC report questions whether Site C can make its 2024 completion date, and concludes the cost “may” exceed $10 billion. It describes the option of suspending work and restarting it in 2024 as the “least attractive of the three scenarios” set out by the government.

Energy Minister Michelle Mungall said Wednesday the report is technical and requires further study, but one thing that is clear is that delaying Site C is not an option that would protect B.C. Hydro ratepayers from unnecessary rate increases.

In the legislature Wednesday, Peace River South MLA Mike Bernier called on the government to make a decision within a month, to provide certainty to the people working at Site C. Eight years of study done under the B.C. Liberal government, and court decisions saying consultation with affected people was adequate, mean no further delay is needed, Bernier said.

Green Party leader Andrew Weaver said the report “should be viewed as the final nail in the coffin of Site C,” due to potential cost overruns and the B.C. Liberal government’s rush to secure fixed-term electricity supply to liquefied natural gas projects.

“The one issue of concern” is the transfer of the $4 billion cost of scrapping Site C to be added to the provincial debt, Weaver said.

Horgan’s government instructed BCUC to come up with cost estimates for completing the dam, pausing construction for a more thorough review of alternatives and future electricity demand, or stopping it and restoring the project area.

The report estimates the cost of shutting down Site C and remediating the project area to be $1.8 billion, plus the cost of finding alternative energy sources to meet demand, on top of the $2 billion already spent.

“The suspension and restart scenario adds at least an additional $3.6 billion to final costs and is by far the most expensive of the three scenarios,” the report states.

The BCUC panel also concluded that “increasingly viable alternative energy sources such as wind, geothermal and industrial curtailment could provide similar benefits to ratepayers as the Site C project with an equal or lower unit energy cost.”

Horgan said Tuesday that one more round of consultation with area Indigenous communities will be conducted next by Indigenous Relations Minister Scott Fraser, and then cabinet will consider its options.

B.C. Hydro has already awarded the major contracts for the powerhouse, river diversion and main civil works in the riverbed.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislatureSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

LETTER: Langley peace advocates call on Canada to stop exporting weapons of war

Ninety per cent of casualities from armaments are civilians, two local residents say

Fundraising during a pandemic: how Langley’s Driedger Farms handled it

Second annual event for Langley Hospice raised $3,500

LETTER: Speeders have Fort Langley resident concerned about safety

Letter writer says it’s only a matter of time before something really bad happens if change isn’t made

Vancouver Giants co-owner Michael Bublé to receive Order of B.C.

Canadian artist joined ownership group in December 2008

Real estate sales spike in Langley in July

People are busy buying and selling properties again

B.C. records 30-50 new COVID-19 cases a day over weekend, no new deaths

Many of those testing positive were identified by contact tracing for being linked to other confirmed infections

Five B.C. First Nations call out Canada for ‘discriminatory’ food fish practices

West Coast nations say government ignoring court-won right to chinook and coho

Salmon arrive in larger numbers at Big Bar landslide

Arrival follows historic hihg-water levels that halted migration runs

B.C. marine ecologist wants Canada to sink its teeth into shark protection

Gulf Islands scientist says top predator under shocking threat from human behaviour

Rent-relief program becomes new front in fight between Liberals, opposition

Opposition trying to draw parallels between decision to have Canada Mortgage and Housing Corp. run program and the WE controversy

Ottawa sets minimum unemployment rate at 13.1% for EI calculation

Statistics Canada says the unemployment rate was 10.9 per cent in July

$45K in donations received after couple’s sudden death in Tulameen

Sarah MacDermid, 31, and Casey Bussiere, 37, died August long weekend

COVID-19 exposure at Surrey rave prompts warning from Fraser Health

Party was held at Royal Beauty Supply in Whalley

Most Read