Slope stabilization work continues on the north bank of the Peace River for the Site C dam, September 2017. (B.C. Hydro)

UPDATE: Decision time for John Horgan on Site C dam

Energy Minister Michelle Mungall says delaying it is off the table

Premier John Horgan’s cabinet intends to make a decision on whether to continue building the most expensive construction project in B.C. history by the end of 2017.

The B.C. Utilities Commission released its independent report on the project Wednesday, ordered by Horgan to fulfil a promise he has repeated many times since becoming NDP leader.

The BCUC report questions whether Site C can make its 2024 completion date, and concludes the cost “may” exceed $10 billion. It describes the option of suspending work and restarting it in 2024 as the “least attractive of the three scenarios” set out by the government.

Energy Minister Michelle Mungall said Wednesday the report is technical and requires further study, but one thing that is clear is that delaying Site C is not an option that would protect B.C. Hydro ratepayers from unnecessary rate increases.

In the legislature Wednesday, Peace River South MLA Mike Bernier called on the government to make a decision within a month, to provide certainty to the people working at Site C. Eight years of study done under the B.C. Liberal government, and court decisions saying consultation with affected people was adequate, mean no further delay is needed, Bernier said.

Green Party leader Andrew Weaver said the report “should be viewed as the final nail in the coffin of Site C,” due to potential cost overruns and the B.C. Liberal government’s rush to secure fixed-term electricity supply to liquefied natural gas projects.

“The one issue of concern” is the transfer of the $4 billion cost of scrapping Site C to be added to the provincial debt, Weaver said.

Horgan’s government instructed BCUC to come up with cost estimates for completing the dam, pausing construction for a more thorough review of alternatives and future electricity demand, or stopping it and restoring the project area.

The report estimates the cost of shutting down Site C and remediating the project area to be $1.8 billion, plus the cost of finding alternative energy sources to meet demand, on top of the $2 billion already spent.

“The suspension and restart scenario adds at least an additional $3.6 billion to final costs and is by far the most expensive of the three scenarios,” the report states.

The BCUC panel also concluded that “increasingly viable alternative energy sources such as wind, geothermal and industrial curtailment could provide similar benefits to ratepayers as the Site C project with an equal or lower unit energy cost.”

Horgan said Tuesday that one more round of consultation with area Indigenous communities will be conducted next by Indigenous Relations Minister Scott Fraser, and then cabinet will consider its options.

B.C. Hydro has already awarded the major contracts for the powerhouse, river diversion and main civil works in the riverbed.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Just Posted

WIND WARNING: Metro Vancouver expecting 100 km/h gusts Saturday night

Environment Canada issues warns of possibly dangerous conditions

VIDEO: Remember the Voyageurs at Fort Langley

Two-day historical festival underway

Fraser Health asking taxpayers for millions more in health care capital funding

Health authority wants Fraser Valley taxpayers to triple annual contribution to $5.75 million

Guilty plea issued in case where man, 86, was assaulted and robbed

Hughie Stump pleads guilty to break-and-enter in relation to Abbotsford incident

UPDATE: 24-year-old Lovepreet Dhaliwal ID’d as victim in targeted Abbotsford shooting

Location of shooting the same as where innocent bystander Ping Shun Ao killed in 2015

Mom delivers plastic mats to Langley’s homeless

Jenifer Kosman fashions sleeping mats from plastic grocery bags

Orange crush: Vancouver Giants blanked by Portland Winterhawks

Saturday’s 2-0 setback marks first regulation loss for G-Men in 10 games

VIDEO: Thousands join women’s march events across B.C.

Today marks one year since the first Women’s March on Washington

Two Canadians, two Americans abducted in Nigeria are freed

Kidnapping for ransom is common in Nigeria, especially on the Kaduna to Abuja highway

Are you ready for some wrestling? WWE’s ‘Raw’ marks 25 years

WWE flagship show is set to mark its 25th anniversary on Monday

B.C. woman who forged husband’s will gets house arrest

Princeton Judge says Odelle Simmons did not benefit from her crime

Snow warning in effect for the Coquihalla

A snowfall warning is in effect from Hope to Merritt as slush and snow is expected on highways this weekend

Vancouver hoping free public Wi-Fi expansion will drive tourism dollars

Mayor Gregor Robertson says expansion bolsters its “leading Smart City” status

Liberals’ 2-year infrastructure plan set to take 5: documents

Government says 793 projects totalling $1.8 billion in federal funds have been granted extensions

Most Read